Customer – Local independent food packager
Objective – Increase capacity and speed
Project – Upgrade existing bottling line design and build new equipment, add metal detection devices, process control upgrades, up grade capper and filling unit, install line shaft drive, while integrating new system with existing equipment.

Features – Project completed in 3 months with down time never exceeding 4 days. Upgrades installed at night and weekends.
Customer experienced a 30% increase in capacity and 80%
efficiency throughout.